42. The authorization holder must, at least 7 days before the start of the work, notify the Minister of the date anticipated for the start of the work.
Where the holder cannot comply with the start date, the holder must as soon as possible notify the Minister, in writing, indicating the reasons justifying the delay. The holder must also notify the Minister, in writing, of the new expected date for the start of the work if the date is expected within 7 days of the first notice of delay or of the holder’s intent not to proceed.
1251-2018O.C. 1251-2018, s. 42.